Project started on March 6th, 2012, completed on October 10th, 2012 and was handed over to the investor on November 20th, 2012. The project was executed by HOCHTIEF CZ a. s. After agreement with the investor the works were adjusted in manner that would not disrupt the operation of school, teaching and planned school-leaving examinations. During summer holiday the work intensified. At the beginning of the new school year only finishing works were executed.
The project Thermal insulation of Secondary nursing school in Karviná required an investment exceeding 15 mil. CZK (EUR 600 000). Major portion of the investment was financed from the European Union. The Region of Moravia-Silesia and the State Environmental Fund also participate on financing.