Prague, External Prague ring road, 514 Slivenec - Lahovice

This mentioned part will be one of the sections in the prepared south-western Prague ring road between highways D1 and D5.

Information:

Location: Prague
Investor: Ředitelství silnic a dálnic ČR
Realization: Joint-venture of companies STRABAG a.s., HOCHTIEF Construction AG, Max Bögl a Josef Krýsl, kom. spol.
Type: New construction
Construction time: 2006 - 2010
Main indicators:  
Description: The ring route will include a steel bridge over the Lochkovské Valley – behind the Radotín cement factory, two parallel tunnel tubes with the length of 1.5 km – three-lane ascending and two lane descending, a two kilometer long flyover bridge over the Berounka Valley and a large interchange crossroad with Strakonická slip road.