Length of the reconstructed road is 1 261 m. The reconstruction is divided into 4 stages. The reconstruction project includes reconstruction of road surface and simultaneous exchange of existing sewerage, construction of new rain-water sewers and water-lines, relaying of buried services and especially widening of the existing road. Therefore it is also necessary to provide new protective pipes since those existing end at the end line of the old street.
Date of start of works on the 1st stage is 30th June 2005. The originally set date was April 2005, but there were some unclear issues in the project design, it was then postponed to July.
The 1st stage includes demolition of the existing road, construction of sewerage and water-lines; the company Strabag will subsequently lay a part road surface (in total 343,6 m).
It is planned exchange of all services will be executed before suspension of works for winter period. Suspension of works is expected from December 2005 to February 2006.
The 4th stage of the project includes landscaping works.
Date of handover of the project is planned in late May 2006.